Short term revamping of No. 6 blast furnace in Chiba Works*
Faible durée de réfection du haut-fourneau 6 de Kawasaki-Chiba
The Chiba No. 6 blast furnace was blown-in in June 1977 and finished its first campaign of 20 years and 9 months in March 1998. The revamping for the second campaign was executed in a short period of only 62 days and to realize this programme, a new revamping method was developed. This method consists in disassembling the furnace body in several blocks and of assembling four prefabricated blocks by a jack-up system.
© La Revue de Métallurgie 1999
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.