Relining of the Sidmar blast furnace A
In 2003, Sidmar commissioned the renewed blast furnace A at the Ghent works. It will operate together with the existing blast furnace B to provide an ironmaking capacity of 4.5 million t/year under optimal circumstances. The furnace was designed and constructed under an engineering contract with Paul Wurth and by a joint Sidmar engineering and project team. This will be the fifth campaign of blast furnace A. This paper describes the relining operations.
© La Revue de Métallurgie, 2004
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.